Blog Post #10
Good Morning! It's been about a month since our last update, but that just means we have been very busy!
Since our last posting the site has continued to progress. The contractor has continued to clean and clear building materials showing the true size of the site without the structures still standing. We have been able to demolish Abrasives 4 North, Abrasives 4 South the jet mill and we have begun demolition of Abrasives 8. 21 rail cars have left the site that would have equated to 114 tractor trailer trucks leaving with approximately 4,200,000 pounds of debris. Over the next few weeks we will continue to work through demolition of Abrasives 8 and Plant 6. Stay tuned for progress photos.